Delay to completion
The term ‘delay to completion’ can be used to mean either:
- Delay to the date that the contractor planned to complete its works,
- Delay to the contract completion date.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, uses the expressions ‘employer delay to completion’ and ‘contractor delay to completion’, both of which mean delay to a contract completion date.
The term ‘delay to progress’ means a delay which will cause delay to the contractor’s progress but without causing a contract completion date to be missed. It is either an employer delay to progress or a contractor delay to progress.
Ref Society of Construction Law Delay and Disruption Protocol. https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Certificate of non completion.
- Completion.
- Completion date.
- Concurrent delay.
- Contract completion date.
- Contractor delay.
- Contractor’s planned completion date
- Defects liability period.
- Employer delay,
- Extension of time.
- Liquidated and ascertained damages.
- Loss and expense.
- Practical completion.
- Progress of construction works.
- Sectional completion.
- Time at large.
- Topping out.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.